top of page

Status Update – August 2020

Foxconn’s Industrial Construction Work in Area 1

WisconnValley Science & Technology Park

Mount Pleasant, WI – Work on remaining sitewide activities is projected to complete as scheduled

Fab Main Lobby

Fab:

  • Has received a Certificate of Occupancy

  • Final Phase 0 preparations are completing

  • Associated landscaping and paving will be completed soon

  • Code required work in the Phase 1 spaces has been designed and will begin soon

PSS:

  • Commissioning is complete

  • Permanent Power to PSS is established

Fab North & East Facades
 

Fii Projects Update

HPCDC Sheer Core &Steel

Smart Manufacturing Center (“SMC”):

  • Interior painting underway

  • Continuing drywall throughout

  • Continuing MEP rough-in

  • Starting finishes (flooring and ceilings) on Mezzanine level

  • Continuing site concrete

  • Prepping for paving north parking lot

High Performance Computing Data Center (“HPCDC”):

  • Completed erecting half of steel; continuing steel erection and assembly

  • Equator ring to be set 8/18

  • Continuing lower level MEP rough-in

 

Businesses interested in applying for competitive bids packages with Mortenson for Foxconn’s other facilities such as the Smart Manufacturing Center (SMC) and High-Performance Computing Data Center (HPCDC) are asked to visit wisconnvalley.wi.gov for upcoming opportunities and to register at https://bit.ly/2k9Qn5V. Students, recent college graduates, job-seekers and veterans interested in pursuing careers in fields such as high-performance computing, smart manufacturing, industrial big data, cloud computing, smart display and industrial artificial intelligence are invited to visit foxconnjobs.us to learn more.

Featured Posts
Recent Posts
Archive
Search By Tags
Follow Us
  • Facebook Basic Square
  • Twitter Basic Square
  • Google+ Basic Square
bottom of page