Status Update – September 2020

Foxconn’s Industrial Construction Work in Area 1

WisconnValley Science & Technology Park

Mount Pleasant, WI – Work on remaining sitewide activities is projected to complete as scheduled

Fab Main Lobby

Fab:

  • Phase 0 areas and the “NE Quadrant” land to be turned over to SIO in September

  • Code required work in the balance of the Fab (”Phase 1” spaces) has been designed and will begin soon

PSS:

  • PSS and associated land to be turned over to FEWI in September

Fab North & East Facades
 

Fii Projects Update

HPCDC Sheer Core &Steel

Smart Manufacturing Center (“SMC”):

  • Interior painting continues

  • Continuing drywall – lower levels

  • Setting air handlers

  • Light fixture installation

  • Continue finish work (flooring, ceilings, casework)

High Performance Computing Data Center (“HPCDC”):

  • Completed radiant topping slab

  • Continued slab edge cold formed framing • Pre-assembly of dome top cap

  • Continued channels for insulated glass panels

  • Continued drywall in lower level

  • Continuing MEP:

  • Install on lower level

  • layout & rough-in second floor

  • Started site utilities

 

Businesses interested in applying for competitive bids packages with Mortenson for Foxconn’s other facilities such as the Smart Manufacturing Center (SMC) and High-Performance Computing Data Center (HPCDC) are asked to visit wisconnvalley.wi.gov for upcoming opportunities and to register at https://bit.ly/2k9Qn5V. Students, recent college graduates, job-seekers and veterans interested in pursuing careers in fields such as high-performance computing, smart manufacturing, industrial big data, cloud computing, smart display and industrial artificial intelligence are invited to visit foxconnjobs.us to learn more.

Featured Posts
Recent Posts
Archive
Search By Tags
Follow Us
  • Facebook Basic Square
  • Twitter Basic Square
  • Google+ Basic Square
bottom of page