NEWS

Foxconn’s Industrial Construction Work in Area 1

WisconnValley Science & Technology Park

Mount Pleasant, WI – Work on remaining sitewide activities is projected to complete as scheduled

Fab:

  • Phase 0 areas and the “NE Quadrant” land to be turned over to SIO in Septemb...

Mount Pleasant, WI – Foxconn Technology Group (Foxconn) and its construction manager, Mortenson, announced the structural steel completion of its 100-foot-tall High-Performance Computing Data Center (HPCDC) Globe located within Area 1 Phase 1 of the Wisconn Valley Scie...

In Response to the Spread of COVID-19 in the United States

Mount Pleasant, WI – Foxconn has successfully completed regulatory and quality requirements necessary to begin manufacturing Medtronic Puritan Bennett™ 560 (PB560) ventilators for Medtronic in the United States....

Foxconn’s Industrial Construction Work in Area 1

WisconnValley Science & Technology Park

Mount Pleasant, WI – Work on remaining sitewide activities is projected to complete as scheduled

Fab:

  • Has received a Certificate of Occupancy

  • Final Phase 0 preparations are...

Foxconn’s iAI Institute is offering introductory online iAI courses to help optimize businesses through data-driven and problem-oriented solutions.

Milwaukee, WI –Foxconn Technology Group (Foxconn), today hosted a Smart Manufacturing Web Conference and announced the lau...

Companies aim to produce 10,000 Puritan Bennett™ 560 ventilators together in the United States over the next year; partnership established after Medtronic announces Ventilator Open Source Initiative

DUBLIN & Mount Pleasant, WI – Medtronic plc (NYSE:MDT) and Foxconn Indu...

In Response to the Spread of COVID-19 in the United States

Mount Pleasant, WI – Foxconn Technology Group (Foxconn) announced today that in response to the spread of COVID-19 across the United States and the State of Wisconsin, the company has begun assembling procedural...

Foxconn’s Industrial Construction Work in Area 1, WisconnValley Science & Technology Park

Mount Pleasant, WI – Completion of balance of planned sitewide activities will recommence soon. Guard shack install at select gates has begun.

Fab:

  • Roof and exterior enclosure...

Foxconn’s Industrial Construction Work in Area 1, WisconnValley Science & Technology Park

Mount Pleasant, WI – Construction Status Update

Sitewide activities are largely in winter stabilization mode. Fencing installs and limited other work continues as weather allows.

F...

Vertical Construction and Steel Placement Underway at Smart Manufacturing Center in Mount Pleasant, WI

Please reload

Featured Posts

Less Than One Year Later: Work to Begin on Foxconn Site

April 26, 2018

1/1
Please reload

Recent Posts
Please reload

News Archive
Please reload

Search By Tags
Please reload