Status Update – August 2020

Foxconn’s Industrial Construction Work in Area 1

WisconnValley Science & Technology Park

Mount Pleasant, WIWork on remaining sitewide activities is projected to complete as scheduled

Fab Main Lobby

Fab:

  • Has received a Certificate of Occupancy

  • Final Phase 0 preparations are completing

  • Associated landscaping and paving will be completed soon

  • Code required work in the Phase 1 spaces has been designed and will begin soon

PSS:

  • Commissioning is complete

  • Permanent Power to PSS is established

Fab North & East Facades

Fii Projects Update

HPCDC Sheer Core &Steel

Smart Manufacturing Center (“SMC”):

  • Interior painting underway

  • Continuing drywall throughout

  • Continuing MEP rough-in

  • Starting finishes (flooring and ceilings) on Mezzanine level

  • Continuing site concrete

  • Prepping for paving north parking lot

High Performance Computing Data Center (“HPCDC”):

  • Completed erecting half of steel; continuing steel erection and assembly

  • Equator ring to be set 8/18

  • Continuing lower level MEP rough-in

Businesses interested in applying for competitive bids packages with Mortenson for Foxconn’s other facilities such as the Smart Manufacturing Center (SMC) and High-Performance Computing Data Center (HPCDC) are asked to visit wisconnvalley.wi.gov for upcoming opportunities and to register at https://bit.ly/2k9Qn5V. Students, recent college graduates, job-seekers and veterans interested in pursuing careers in fields such as high-performance computing, smart manufacturing, industrial big data, cloud computing, smart display and industrial artificial intelligence are invited to visit foxconnjobs.us to learn more.