Status Update – August 2020
Foxconn’s Industrial Construction Work in Area 1
WisconnValley Science & Technology Park
Mount Pleasant, WI – Work on remaining sitewide activities is projected to complete as scheduled
Fab:
Has received a Certificate of Occupancy
Final Phase 0 preparations are completing
Associated landscaping and paving will be completed soon
Code required work in the Phase 1 spaces has been designed and will begin soon
PSS:
Commissioning is complete
Permanent Power to PSS is established
Fii Projects Update
Smart Manufacturing Center (“SMC”):
Interior painting underway
Continuing drywall throughout
Continuing MEP rough-in
Starting finishes (flooring and ceilings) on Mezzanine level
Continuing site concrete
Prepping for paving north parking lot
High Performance Computing Data Center (“HPCDC”):
Completed erecting half of steel; continuing steel erection and assembly
Equator ring to be set 8/18
Continuing lower level MEP rough-in
Businesses interested in applying for competitive bids packages with Mortenson for Foxconn’s other facilities such as the Smart Manufacturing Center (SMC) and High-Performance Computing Data Center (HPCDC) are asked to visit wisconnvalley.wi.gov for upcoming opportunities and to register at https://bit.ly/2k9Qn5V. Students, recent college graduates, job-seekers and veterans interested in pursuing careers in fields such as high-performance computing, smart manufacturing, industrial big data, cloud computing, smart display and industrial artificial intelligence are invited to visit foxconnjobs.us to learn more.