Fii Projects Status Update – March 2021

HPCDC CONSTRUCTION STATUS UPDATE

SMC SITE PHOTO
HPCDC Interior
  • Complete drywall installation and paint on all levels

  • Continue start-up and testing of mechanical equipment

  • Complete installation of moss wall

  • Complete installation of polished concrete in Lower Level andLevel 3

  • Begin painting center core and monument stairs

  • Begin installation of glass roof at front vestibule

  • Complete installation of hard tile in kitchen and lobby areas

  • Complete installation of interior building signage


WHAT TO EXPECT IN MARCH

  • Substantial Completion: March 12, 2021

  • Owner to begin furniture and TV installation

  • Complete polished concrete on Level 1

  • Complete mechanical start-up and testing

  • Complete egress path around building

Businesses interested in applying for competitive bids packages with Mortenson for Foxconn’s other facilities such as the Smart Manufacturing Center (SMC) and High-Performance Computing Data Center (HPCDC) are asked to visit wisconnvalley.wi.gov for upcoming opportunities and to register at https://bit.ly/2k9Qn5V. Students, recent college graduates, job-seekers and veterans interested in pursuing careers in fields such as high-performance computing, smart manufacturing, industrial big data, cloud computing, smart display and industrial artificial intelligence are invited to visit foxconnjobs.us to learn more.