Status Update – September 2020
Foxconn’s Industrial Construction Work in Area 1 WisconnValley Science & Technology Park Mount Pleasant, WI – Work on remaining sitewide activities is projected to complete as scheduled Fab: Phase 0 areas and the “NE Quadrant” land to be turned over to SIO in September Code required work in the balance of the Fab (”Phase 1” spaces) has been designed and will begin soon PSS: PSS and associated land to be turned over to FEWI in September Fii Projects Update Smart Manufacturing


Foxconn “Tops Off” 100-Foot-High Performance Computing Data Center Globe
Mount Pleasant, WI – Foxconn Technology Group (Foxconn) and its construction manager, Mortenson, announced the structural steel completion of its 100-foot-tall High-Performance Computing Data Center (HPCDC) Globe located within Area 1 Phase 1 of the Wisconn Valley Science and Technology Park (WVSTP) in Mount Pleasant, WI. Foxconn and Mortenson will soon begin the process of installing 642 pieces of glass through Q4 2020. To date, Foxconn has invested approximately $750 millio