Status Update – October 2020
Foxconn’s Industrial Construction Work in Area 1 WisconnValley Science & Technology Park Mount Pleasant, WI – Remaining site development work is complete. Most of Area 1 land is now turned over to SIO/FEWI Fab: Phase 0 areas to be turned over to SIO in November Code required work in the balance of the Fab (”Phase 1” spaces) has begun and is schedule to complete in 1Q2021 PSS: PSS and associated land has been turned over to SIO/FEWI Fii Projects Update Smart Manufacturing Cent