Fii Projects Status Update – March 2021
HPCDC CONSTRUCTION STATUS UPDATE Complete drywall installation and paint on all levels Continue start-up and testing of mechanical equipment Complete installation of moss wall Complete installation of polished concrete in Lower Level andLevel 3 Begin painting center core and monument stairs Begin installation of glass roof at front vestibule Complete installation of hard tile in kitchen and lobby areas Complete installation of interior building signage WHAT TO EXPECT IN MARCH