Foxconn’s Industrial Construction Work in Area 1, WisconnValley Science & Technology Park

Mount Pleasant, WI – Completion of balance of planned sitewide activities will recommence soon. Guard shack install at select gates has begun.
Fab:
Roof and exterior enclosure work are nearly complete
Mechanical, electrical and plumbing work as well as interior finish work is proceeding per schedule
PSS:
Major electrical equipment has been installed
Commissioning is now underway
SIO Procurement Summary
Power Substation – Awarded
Fab Building Enclosure, Additional Site Work – Awarded
Fab Building Interiors – Awarded
Fab MEP –Initial Phase – Awarded
Fab Turnkey Systems, additional MEP Systems – Pre-Bid Meeting Held
Information regarding these bid packages and all current bid opportunities for the project, as well as previous bid awards for work at the WVSTP to date can be found at: https://wisconnvalley.wi.gov/Pages/ScienceTechPark.aspx. Businesses interested in applying for competitive bids packages with Mortenson for Foxconn’s other facilities such as the Smart Manufacturing Center (SMC) and High-Performance Computing Data Center (HPCDC) are asked to visit wisconnvalley.wi.gov for upcoming opportunities and to register at https://bit.ly/2k9Qn5V. Students, recent college graduates, job-seekers and veterans interested in pursuing careers in fields such as high-performance computing, smart manufacturing, industrial big data, cloud computing, smart display and industrial artificial intelligence are invited to visit foxconnjobs.us to learn more.